AI Buildout Fuels Warehouse Demand Near Data Centers

Why This Matters to Distributors: Electrical, HVAC and building materials distributors can supply the same data center for years. Contractors need switchgear, cooling equipment and other materials delivered in phases during construction. Once the facility opens, operators need replacement parts on short notice. Serving both can mean stocking inventory in markets where equipment makers, logistics providers and data center operators are also competing for warehouse space.

Companies that build, equip, and operate data centers leased 50 million square feet of U.S. industrial space through September, 113% more than in all of 2025, according to a report Cushman & Wakefield announced Nov. 24. Construction and building suppliers accounted for 30% of that space. The analysis includes data centers that support artificial intelligence, cloud computing, and other workloads.

The report also found that U.S. imports of AI-related equipment, parts and components rose 62% year over year to $659 billion. Equipment moving from ports to data center campuses often passes through warehouses and distribution networks. Data center-related users accounted for a record 14% of new U.S. industrial leasing in the third quarter, based on the firm’s analysis of tenants occupying at least 50,000 square feet.

Data center development is creating a physical supply chain that extends well beyond the campus itself,” said Jason Price, Cushman & Wakefield’s head of Americas logistics and industrial research. The report identifies construction and building suppliers, equipment and component manufacturers, and third-party logistics providers as the main groups leasing space to serve data centers.

Warehouse Demand Spreads Beyond Established Hubs

Columbus, Ohio, Phoenix, Atlanta, and Dallas-Fort Worth accounted for more than 32 million square feet of data center-related industrial leasing through September. Combined leasing in Austin-San Antonio, Kansas City, Reno, and West Texas rose 274% from a year earlier. Kansas City alone accounted for 2.2 million square feet.

Third-party logistics providers took 11 million square feet of space tied to data center customers through September. Large data center operators signed six leases of more than 500,000 square feet each to store and distribute equipment and parts, primarily in Dallas-Fort Worth, Atlanta, Kansas City and Charlotte, North Carolina. Cushman & Wakefield said companies with early visibility into planned campuses can secure warehouse space before construction begins.

Replacement Parts Can Sustain Demand After Construction

Cushman & Wakefield expects maintenance and equipment replacement to sustain much of the demand for warehouse space. For distributors, the inventory commitment changes when a campus opens. A scheduled switchgear delivery can be staged around a contractor’s installation date. A replacement part for a failed cooling unit may need to be on the shelf nearby before the order comes in. 